Wednesday, April 8, 2009

Week 5 Update

Last week, we finished the deliverables for P1. This week we continued to work towards completion of the P2 deliverables. So far we have a prototype for our survey and a partial set of use cases. Given that P2 is not due until the 18th, we anticipate no scheduling difficulties.

Ongoing tasks:

  • Finish survey: full team
  • Complete use cases: full team

For next week:

  • Create prototype: full team
  • Create activity diagrams: full team

1 comment:

  1. tasks fine, but no times or who is responsible/leading the effort

    ReplyDelete